Jianhua Baogong Tesla prefabricated parts ushered in the tide of demand

Click the blue word of “China Building Materials Information Network” to pay attention to many of our key projects and speed up the recovery of the construction period.

Prefabricated parts usher in the tide of demand.

Jianhua Baogong Tesla has a small peak in the supply of many kinds of products.

Machines in the production workshop roar and workers are accelerating the production of pipe piles, This is Tangshi Jianhua building materials (Shanghai) Co., Ltd.

(hereinafter referred to as Shanghai Jianhua) who urgently added a production team for Tesla phase II project, a key project in Shanghai.

On February 17, Zhang Zhongnian, a salesman of Shanghai Jianhua, received a notice from the design unit that he hoped to provide 30000 meter pipe pile products for Tesla phase II before March 7.

Yu Xiang, deputy general manager of Shanghai region, urgently set up a special team to overcome the adverse factors such as logistics and personnel during the epidemic.

The business personnel and technicians communicated with the customers through remote network technology, quickly organized the workshop workers to start production on the day they received the order, and arranged 10 drivers to provide exclusive services for the site.

On February 22, the first batch of products arrived at the project site safely.

The “rapid response” of Shanghai Jianhua’s quality and quantity assurance service has been fully affirmed by the owner and the design unit.

In fact, this is an epitome of the subsidiaries and production bases of Jianhua building materials group (hereinafter referred to as Jianhua building materials) in the national tide of resumption of work after the epidemic is under control.

The reporter learned that from the coast of the South China Sea to the northern Great Wall, many construction sites are enthusiastic, especially for some key projects.

The employees of Jianhua building materials are trying to recapture the delayed construction period of the epidemic.

Therefore, it has suddenly accelerated a small peak of demand for prefabricated piles and prefabricated components of Jianhua building materials.

At present, behind the current trend of resumption of construction and reconstruction is a series of policies actively supporting industrial development issued by the state and governments at all levels.

The site selection investment in the secondary industry will be released as soon as the end of the first quarter, showing a trend of low in the first quarter and high in the second quarter.

The construction of some landmark major projects in China, such as Zhejiang Petrochemical phase II, Gulei petrochemical and other key industrial projects, has been determined to resume work by the end of February, and the Shenghong refining and chemical integration project of Lianyungang Petrochemical has officially resumed work on February 20.

As a supplier and service provider of these major projects, Jianhua building materials has prepared goods in advance and paid close attention to the construction period.

It has recently begun to provide pipe pile products.

The tide of industrial projects will inevitably lead to the supply tide of prefabricated components, which is determined by the excellent characteristics of prefabricated component series products represented by prefabricated piles.

At present, the owner, general contractor and contractor of the project all hope to quickly restore the suspended and delayed projects affected by the epidemic to the right track, while the negative impact of the epidemic not completely retreating is still on, such as the lack of construction workers in the short term, regional shortage of raw materials, logistics and transportation and other problems are still delaying the progress of resumption of construction.

All kinds of high-quality prefabricated components provided by Jianhua building materials with the characteristics of more speed, better economy have become an important weight for whether we can successfully grab back the construction period and catch up with the progress.

With a bottleneck, it is bound to accelerate change! In fact, during the severe epidemic period, the rapid construction of a large number of emergency epidemic prevention facilities and hospitals represented by “Huoshen mountain” and “Leishen mountain” made the market fully realize the prominent advantages of prefabricated buildings, such as “high degree of mechanization, fast construction speed, less labor and good product quality”.

In February 8th, the National Health Protection Committee and the Ministry of housing prepared the guidelines for the design of New Coronavirus pneumonia emergency treatment facilities (Trial Implementation), and encouraged emergency treatment facilities to give priority to fabricated buildings.

Before the outbreak of the epidemic, support policies and subsidy standards for prefabricated buildings were successively issued throughout the country, and prefabricated demonstration bases and projects across the country and provinces and cities were determined.

The tasks and objectives of prefabricated buildings were clarified to counties and cities, from top-level design to local rules, so that policies could help prefabricated buildings “take root and sprout”.

It can be predicted that as an important direction of transformation and upgrading of China’s construction industry, prefabricated buildings will continue to play an important role in the critical period of accelerating project construction and ensuring the smooth operation of the project after the end of the epidemic! As the first batch of “prefabricated construction industry bases” in the concrete products industry, Jianhua building materials shoulders the industry mission, pays close attention to the pain points, and is based on the R & D and production advantages of concrete precast products.

In the field of industrial construction, we continue to innovate and upgrade product technology and innovate integrated concrete prefabricated solutions to help industrial construction projects quickly seize the construction period and save labor costs after the epidemic! Prefabricated buildings are “good, fast and economical”.

Speaking of the advantages of prefabricated buildings, The relevant person in charge of Jianhua building materials told reporters: “Firstly, the quality of prefabricated concrete components is controllable, the deviation of appearance surface flatness is small, and the concrete strength of prefabricated products can reach C40, which is conducive to improving the instability of concrete quality of traditional cast-in-situ structure; secondly, the construction period is controllable, prefabricated components are produced in factory, and Mechanical hoisting is used for on-site installation, which is safe and convenient, and can greatly reduce the use of labor force and reduce the cost of project construction The period can be free from the influence of natural weather and other factors; The third is energy conservation and environmental protection.

Most of the main parts of the project are prefabricated.

A large number of cement, sand and other dust building materials do not need to enter the construction site, and the construction has little impact on the surrounding urban environment.

For example, the expansion project of Nantong “huoshenshan” Sixth People’s Hospital, which provides prefabricated cable duct and prefabricated cable well product services, took only one and a half days from receiving the notice to the completion of installation.

The assembly speed ensured that the power supply of the project was completed on time, seizing valuable time for epidemic prevention.

” “Taking the electronic plant project of Sichuan Mianyang hanergy group as an example, the construction period planned by the owner of the project is very short.

If the traditional cast-in-situ structure is used, the construction period is expected to be about 3 months, which puts great pressure on the operation cost in the later stage of the project, and the owner urgently needs to find a fast and reliable alternative solution..