Labor service cooperation hotline: 18552614605 general catalogue of Logistics Majors to provide high-quality services 1 Logistics operation equipment and tooling 12 Fabrication of loading scheme 23 Process control 34 Transportation emergency plan 45 Matters needing cooperation 51 Logistics operation equipment and tooling serial number tool name type parameter demand quantity example picture 1 transportation vehicle 13m flat truck 13 * 2.5m, six bridges, maximum load 49 tons, dead weight 17 tons; 2 transportation vehicle 17.5m flat truck 17.5 * (2.7-3) m, six bridges, maximum load 49 tons, dead weight 19 tons; 3 Transportation tooling transportation frame 9 * 2.5m, The maximum load is 40t without 4 transportation tooling transportation frame 4 * 2.5m6 * 2.5m5 hoisting equipment crane 10t16t6 hoisting equipment truck crane 25t7 tooling skid 60 * 80mm8…
2 Fabrication of loading scheme 2.1 line survey in order to ensure the safety of components and send them to the assembly site in time, at least two transportation and distribution lines shall be set.
2.2 loading scheme 4.2.1 check the basic information of components (details, size, number, etc.), and pay attention to the length and direction of reinforcement.
4.2.2 the framing and stacking plan and transportation plan shall be made according to the lifting sequence table of engineering assembly elements.
3.
Process control the quality, quantity and safety of all materials (including tooling, PC components, reinforcement, etc.) within the factory fence shall be in the charge of the logistics engineer; The quality, quantity and safety of all materials (including tooling, PC components, reinforcement, etc.) between the factory fence and the project fence shall be the responsibility of the logistics supplier signing the transportation contract of the project; The quantity and safety of all materials (including tooling, PC components, reinforcement, etc.) arriving in the project fence shall be the responsibility of the receiver, and the quality of all materials after the project receiver signs for receipt shall be the responsibility of the receiver.
4 transportation emergency plan 4.1 abnormal conditions of vehicles in transit: mechanical failure, traffic accident, cargo damage, natural disaster, etc.
4.2 reporting procedure: the driver or attendant shall be the person in charge of the company at the first time to record the abnormal time, place, vehicle condition, simple handling opinions, on-site information, etc; The person in charge shall make preliminary treatment opinions according to the actual situation on site, and notify the driver of on-site treatment if it can be handled directly without affecting the distribution timeliness; In case of emergency or on-site failure to deal with it directly, it is necessary to immediately notify the department head and the project site for coordination.
4.3 rescue measures: the person in charge of the consignor shall be responsible for unified coordination, command, arrangement and handling; The logistics supplier shall prepare 1-2 spare transport vehicles and necessary tools on site at any time.
4.4 disposal measures: 4.4.1 establish an accident emergency team.
When the emergency team leader receives an emergency in the process of transportation, he will send rescue personnel to the site to deal with the incident as appropriate.
4.4.2 the rescue personnel shall report the handling situation to the team leader at any time.
The team leader shall mobilize standby vehicles to complete the transportation task of accident vehicles according to the actual situation.
5.
Matters requiring cooperation 7.1 the receiving party must ensure that the road subgrade in the site must be solid and reliable and that the transportation vehicles run smoothly.
The road width shall not be less than 0.4m, and the turning radius of vehicles shall not be less than 0.13M.
7.2 the receiving party shall make clear the driving route on the site to the consignor according to the total weight of the transport vehicles.
For the positions where the bearing capacity does not meet the requirements (such as basement roof), the receiving party must take reinforcement measures, otherwise the damage to the structure caused by this shall be borne by the receiving party.
7.3 ensure smooth driving of transport vehicles on the site, and arrange more than 2 temporary parking areas for vehicles in each assembly unit.
7.4 deliver the vehicle demand plan 1 # day in advance.
7.5 in order to avoid the impact of logistics emergencies on the project progress, it is recommended that the receiving party set up a temporary storage area within the hoisting range of tower crane, which can store one floor of components, with an area of about 200 # m2.
7.6 the receiving party guarantees that the components of each vehicle will be unloaded within {4 hours after arrival, and the receiving unit shall sign the delivery document in time and return it to the logistics driver.
7.7 the receiving party shall actively cooperate, return the tooling (transportation rack, timbers and tooling, etc.) in time and accurately, and arrange complete loading.
7.8.
In case of any abnormality, please notify the consignor in time.