1 smelting workshop is 139m × 57.5m, 38.85m high and 7 floors, with a total of 155 foundations, including 108 cup foundation, 39 independent foundation, 4 electric furnace foundation and 4 U-shaped track foundations.
The main feature of the workshop is that the steel columns are welded H-shaped steel, the depth of cup foundation is different, the maximum depth is 3.9m, and the maximum section of H-shaped steel is 1550 × 800, minimum section 600 × 200, etc.
The smooth mobilization of the first batch of components marks that the No.
1 smelting workshop of the project officially enters the steel component installation link, and also presses the fast forward key for the subsequent steel component production.
In the near future, on the general Gobi with red willow, Haloxylon ammodendron and Achnatherum splendens, a GCL modern industrial silicon plant constructed by China Metallurgical Tiangong will rise up as the strategic stronghold of northern company in Xinjiang and radiate to the vast land around·.
The building area of No.
The structural form of frame steel structure installation project is frame steel structure.
of China 22nd Metallurgical Group and suppliers, carefully prepared, cooperated with each other and detailed responsibilities, and completed the preliminary work such as submission of component mobilization scheme, signing of safety agreement and basic training of unloading technology.
In order to ensure the smooth mobilization of components, Xinjiang GCL industrial silicon project department, together with MCC heavy industry (Xinjiang) Co., Ltd.
On the morning of April 10, 2022, with the whistle blaring, a transport vehicle carrying 14 tons of steel components successfully arrived at the site of Xinjiang GCL silicon 200000 tons of industrial silicon project.