“I declare that the fabricated prefabricated parts production base of Changzhi company began trial production -” with the instruction of Gao Xicai, general manager of the investment company of Sinohydro Bureau 8, the mixing plant of Changzhi company’s production base, PC component production line and reinforcement production line of plant 1 began joint trial production on the morning of March 30, and successfully produced the first batch of PC components – AB span laminated plates of plant 1 of the base.
The cadres and employees of investment company, Changzhi company, General Contracting Department, supervision, design and other units witnessed this historical moment with excitement.
In September 2018, with the approval of the power construction group, Changzhi company, which is controlled by the eighth Hydropower Bureau and participated by the power construction municipal group, Chizhou Jinqiao investment group and Jiangsu Haofeng company, was officially established to be responsible for the construction and operation of Chizhou prefabricated building prefabrication production base.
The first phase of the base covers an area of 400 mu, which is mainly composed of three functional areas: component forming area, concrete production area and auxiliary production area.
The collective plan is to build two PC factories, each with an annual design capacity of 200000 cubic meters and a total annual design capacity of 400000 cubic meters.
The planning, construction and operation of Chizhou prefabricated building production base of Changzhi company is an important measure for Sinohydro Bureau 8 to comply with the national concept of green development and optimize the strategic layout of enterprises.
It is also a major investment decision for Sinohydro Bureau 8 to build an investment and construction group with the most industry characteristics.
The construction and operation management of Changzhi company is highly valued by the local government, the eighth Bureau of hydropower and investment company.
The government leaders of Chizhou City and Guichi District have visited the base for investigation and guidance for many times, and actively taken measures to solve the actual difficulties of enterprises.
Zhu Suhua, chairman of Sinohydro Bureau 8 and Jiang Qinghua, general manager of Sinohydro Bureau 8, and other leaders are concerned and intelligent.
They have repeatedly connected with the high-level government and provided all-round support such as technology and coordination.
At the same time, the investment company actively allocates excellent talents to build a long intelligence team; Personnel from functional departments are stationed in Changzhi to escort the development of Changzhi.
Once established, Changzhi company adheres to first-class standards and levels in design, construction and equipment, and defines the goal of “building a national prefabricated construction industry demonstration base integrating production, learning and research”.
With the care of all parties, Changzhi company began various preparations and construction work.
From October 1, 2018 to March 28, 2019, when the PHC test pile of No.
1 plant of the production base was commissioned and linked, the trial production conditions were initially met, and then to March 30, the trial production of the first batch of PC components was successful.
In these days, there is not a day that is not soaked by the sweat of the intelligent builders.
In the six months since the commencement of the project, the rainy weather has accounted for three quarters, which has seriously affected the civil engineering and floor construction.
In addition, the construction also faces difficulties such as high progress pressure and many unsafe factors.
However, all participating units adhere to quality standards, increase resource investment, straighten out work ideas, strengthen internal management and performance appraisal, and supervise the implementation of the work to the end.
Changzhi also organized all participating units to carry out labor competitions to encourage all builders to eliminate obstacles and make concerted efforts to advance towards the predetermined goal.
Gao Xicai pointed out at the trial production ceremony: after overcoming various difficulties and experiencing the bad weather of frost, rain and snow, we have seen a rainbow for the first time.
Looking back on the past, there are thousands of feelings; Looking forward to the future, we are confident.
The development direction has been made clear, but the task in the future is still arduous.
All participating units and employees should not relax.
They should continue to make efforts, resolutely realize the index tasks assigned by the eighth Hydropower Bureau and the investment company, and strive for the formal operation of the prefabricated parts production base of Changzhi company! Text: Liu Huiyong, Luo Mengdie, Li jietu: Wang zhenxue, Tang Songbai, Chen Hanlin editor: he Peiyao..