Click on the top ♂ Longan live broadcast plus attention! On the morning of April 1, the live broadcast of the hot tourism interview on the home page, the beam bridge components used for the Gaozhou section of Yunnan-Maoming Expressway were safely transported to Gaozhou from Wuhan, Hubei Province.
Reporter Che Yanbing: “The reporter is now at the mixing station of the project department of the TJ14 section of Yun-Mao Expressway, and under the escort of the relevant departments of our city, three transport vehicles have successively delivered the component materials to the site.” The staff of the relevant units of transportation, health, public security, and disease control in our city have made various preparations for epidemic prevention in advance.
The steel plate composite beam bridge components to be transported by Wuhan Wuchuan Heavy Engineering Co., Ltd.
are transported to the east bank expressway exit of Baotou-Maoming Expressway, and the staff escort transport vehicles are transported to the construction site of Hehua Town of Yunnan-Maoming Expressway through the east bank, Dajing, Nantang and Shiban.
Wu Zongjin, deputy director of the municipal health bureau, said: “According to the management work guidance of the provincial headquarters on the transportation personnel from Hubei to Guangdong, the staff should first verify their health code, then conduct a temperature test, and then ask about their physical condition.
After confirming their physical condition, they will start unloading, and then carry out comprehensive disinfection.” Yunnan-Maoming Expressway construction project is a key project in our province.
The project has a group of steel plate composite beam bridge components belonging to Laowu Village Bridge in Hehua Town, which cannot be transported due to the impact of epidemic prevention and control policies in Hubei Province and Wuhan City.
The COVID-19 prevention and control headquarters in Guangdong Province sent a letter to the COVID-19 prevention and control headquarters in Hubei Province, and the COVID-19 prevention and control headquarters in Wuhan City took active measures to transport construction materials to Gaozhou.
Meng Hairong, the person in charge of the construction site of the steel plate girder of the Laowucun Bridge, said: “If this batch of materials cannot be delivered, the subsequent construction cannot be carried out.
This batch of materials can at least allow us to complete the construction of a span of bridge, which is expected to be completed in about half a month.” Source: Gao Zhou Guangshi Chief Editor: Wu Hongpei First Review: Qiu Xiaoling Final Review: Ma Linhao.
.