December 25, 2024

Dismantling of the Four Lions Pavilion: part of the components are damaged and three 400-year-old cultural relics are intact

The large beam and the stone components above the center of the four lions pavilion in Paifang Street have been completely dismantled.

The removed inter-center crossbeam is completely broken.

▼ At that time, the concrete mixer truck was pulled to the south when it exited, the tension side was opened, and the compression side was relatively dense in the north.

Now, the demolition process is obviously folded into two, and the stone is very hard—— Wu Guotai, senior engineer of the municipal architectural design institute, currently believes that the heart-to-heart crossbeam has been reconstructed according to the raw materials, original structure and original technology as far as possible.

In the process of disassembly, some small stone components were also damaged.

▼ Fortunately, three 400-year-old cultural relic stone components are intact, and two small stone components are temporarily stored in the municipal museum.

▼ Stone components such as upper eave roof and lower eave roof are not damaged.

▼ In the early stage of disassembly, the principle of keeping the large and unloading the small is followed, some things with variable cross-section and easy to be damaged are forced to be damaged, and there are several column top buckets currently seen.

These construction units have made detailed records one by one, and have been actively preparing in the factory—— Wu Guotai, senior engineer of the municipal architectural design institute, said that the construction party will take protective measures for the removed stone components, and will continue to carry out the restoration and installation work after the damaged stone components are completed.

One is to thoroughly clean the residual slurry on the surface of the components that can be reset and installed on the site, including the vertical groove fixed on the structure, until it is smooth.

On the other hand, when the components prepared in the factory arrive, they should be thoroughly inspected to see if there are any slag or defects—— Wu Guotai, senior engineer of the municipal architectural design institute, is expected to complete the renovation project of the Four Lion Pavilion before the National Day this year.

During the period, traffic control will continue to be implemented on the section from Changli Road to Xima Road in Paifang Street, and all vehicles are prohibited from entering.

News review: Four Lion Pavilion is expected to be repaired by the end of October! (Event timeline attached) Articles originally written by the official account of “Chaozhou TV”, declined without authorization
.