On April 9, the barge carrying the 3000t crane boom of the Three Gorges left Nantong Zhenhua heavy loading dock.
All components of the project have been completed and successfully shipped to the shipyard designated by the owner.
The 3000t crane of the Three Gorges is designed and built by Zhenhua heavy industry to meet the needs of the Three Gorges material and equipment company’s deep sea unit capacity of 10MW and the development of Shanghai Shangfeng power project.
The crane has a fixed lifting capacity of 3000 tons at the stern and a full swing lifting capacity of 2400 tons.
It is a full return swing crane.
After the commencement of the project, the project team, adhering to the spirit of “only thinking of ways for success, not finding reasons for failure”, overcame the impact of typhoon, epidemic situation and material delay, focused on optimizing the track bearing surface machining, track manufacturing and processing technology and the overall assembly and closing process of truss frame components, and completed the construction and delivery of all components with all-round quality and quantity within 13 months according to the contract requirements, fully demonstrating the speed of Zhenhua.
At present, the final assembly of the project is just as scheduled, and the subsequent project will enter the commissioning stage.
Text: Cai Weiyue picture: Yu Liangliang, Chen Hao editor: Lu Yinxuan click “looking” to give me a little yellow flower..