Project dynamics | the first batch of steel members of Cote d’Ivoire bridge project were shipped smoothly

On April 16, the first batch of steel components of Cote d’Ivoire steel structure project undertaken by Nantong Zhenhua heavy equipment Co., Ltd.

were successfully loaded and shipped out of the port at the wharf of Nantong Branch.

The first batch of steel members includes 37 box girders of the main bridge, 29 drainage tanks and 10 supporting material boxes, with a total shipment of 76 tons and about 4760 tons.

At the beginning of the project, the project team publicized and implemented the project construction requirements in advance, and all staff learned the construction grade requirements of the European standard en1090-exc4.

Facing the differences in living habits at home and abroad, the project team overcame many adverse factors.

Under the leadership of the company’s leaders, the project team carried forward the spirit of “only thinking of ways for success, not finding reasons for failure”, sorted out the drawing list in advance, followed up the material supply progress in time, and comprehensively guaranteed the smooth completion of steel beam fabrication and coating.

On April 6, the project officially started hoisting and loading to the outer ship.

Under the guidance of government departments, we should do a better job in beam section binding while doing a good job in epidemic prevention.

“It’s tiring to change three sets of epidemic prevention work clothes per person every day.

It’s tiring, but it’s the most important to make the workers feel at ease, safe and secure, eat well and sleep soundly.” Li Feng, deputy leader of the project shipment assault team, said.

Project introduction Cote d’Ivoire Cote d’Ivoire bridge project crosses the Cote d’Ivoire Bay in Abidjan and connects the Cote d’Ivoire embassy area and Prato administrative and commercial district.

It is one of the important projects for the regulation and comprehensive development of the Cote d’Ivoire Bay.

After the completion of the project, it will become the largest cable-stayed bridge in West Africa and a local landmark project.

It is another livelihood and well-being project promised by the Ivorian government to Abidjan residents.

The main bridge steel beam constructed by the company has a total length of 630 meters and is divided into 56 sections.

The total weight of the steel beam is about 7500 tons and the weight of the auxiliary structure is about 1500 tons.

The project team makes every effort to build a high-quality project and contribute to the consolidation and deepening of China Kuwait friendship.

Text: LV Xianhu, Bao Huazhong, Jiang Zhengdao picture: Li Feng editor: Xu Jinxin..