The restoration of the damaged “Confucian School of Confucianism” archway in the Memorial Archway Street has attracted much attention.
What about the current situation? ↓↓↓↓↓↓ The reporter learned that the remanufactured damaged components have been completed.
Today, the relevant personnel began to install the components of the memorial archway.
The entire repair project is expected to be completed before the National Day, when the road will resume normal traffic.
At more than nine o’clock this morning, the reporter saw at the construction site that the memorial archway of “Confucianism” was surrounded by iron sheets.
There was a crane among the iron sheets.
The crane was slowly lifting a stone component.
Several constructors stood on the four stone columns of the archway, paying close attention to the stone components.
Then, the stone component rose to the mid air and slowly moved to the installation position.
Several construction personnel immediately stabilized the stone component and assisted the crane to accurately install the stone component.
The reporter noticed that the damaged main beam in the middle of the archway has been installed.
According to the staff of Chaozhou No.
2 Construction and Installation Corporation, in order to ensure the smooth progress of the memorial archway repair project, previously, except for the four big stone pillars of the memorial archway, all other components were removed.
Some components to be remade have been fabricated and transported to the construction site for installation.
Other components that do not need to be remade are still retained for reinstallation.
The damaged components to be remade this time shall be made of the same materials as the original ones.
The worker said that since the stone components and stone carving components of the archway are connected by mortise and tenon, the main beam in the middle must be installed first, and the components on the left and right sides must be installed from bottom to top.
After installation, it shall be fixed with cement.
The most difficult part to install is the large roof of the archway.
The large roof not only has the heaviest quality, but also has the most joints with tenons and mortises of all parts.
During the installation of the archway components, the constructors need to adjust their positions at the four corners of the archway and cooperate tacitly to ensure that the components can be closely combined.
The staff of Xiangqiao Street Urban Management Office reminded the public that the repair project of the memorial arch of “Confucianism” is expected to be completed before the National Day.
Before the completion of the project, traffic control will be implemented on the section from the intersection of Changli Road in Paifang Street to the intersection of Xima Road, and all vehicles are prohibited from entering.
Please pay attention to safety and drive around.
(Article/reporter Li Canxia intern Chen Xuelin/reporter manor of our newspaper) Recommended reading ▶ Typhoon 19 is coming! Chaozhou will welcome the typhoon “doubles”? Don’t panic! The next weather in Chaozhou is ▶ The result of the slogan collection of Chaozhou’s “six cities create together” city image has been announced! Cheer you up and leave again ↓↓↓↓↓ Editor: Cai Fuxin..