The HRC carbon fiber building template is a new type of template system independently developed by HRC (China Hengrui). It is mainly made of high-performance lightweight carbon fiber and synthetic resin as the main raw materials, and processed through the non woven pressing carbon fiber process. Compared to the aluminum alloy building formwork system, carbon fiber building formwork is lightweight (18 kg/㎡), cost-effective, and has technical advantages such as fast installation speed, low construction noise, and recycling. In addition, carbon fiber building formwork has much lower carbon emissions throughout its lifecycle than aluminum alloy building formwork, responding to the requirements of low-carbon environmental protection and green construction..
Construction process: measurement and laying out → reinforcement binding of shear walls → installation of wall and column formwork → installation of beam formwork → installation of floor formwork → correction and reinforcement, formwork acceptance → reinforcement binding of beams and slabs → reinforcement acceptance → pouring of concrete → dismantling of formwork → transportation to the next floor.
(2) After the vertical correction of the wall body is completed, the bottom formwork of the floor beam is installed. After the vertical correction, the side formwork of the beam is installed;.
(3) Before installing the floor template, check that the diagonal lines are correct. After the support poles are erected, arrange them in parallel one by one. First, fix them temporarily with pins, and finally tighten the pins uniformly. After the installation of all templates is completed, the overall calibration, reinforcement inspection and acceptance shall be carried out;.
(4) After the concrete strength meets the requirements for demolding, remove the formwork and immediately carry out cleaning work. The cleaned formwork is transported to the next installation point for stacking..