December 25, 2024

Capping of the main structure of the first cast steel structure hospital project in Hefei

On January 11, with the last steel beam slowly lifted and successfully installed and positioned, it marked that the main structure of Anhui hospital project of pediatric hospital affiliated to Fudan University was capped.

Lifting from the foundation rigid column to the capping of the main structure, it takes only 90 days to complete the hoisting construction task of more than 16000 tons of steel structure, which fully reflects the construction advantages of cast steel structure, such as fast construction speed, high component processing precision and accurate installation size.

Compared with concrete structure, cast steel structure has lighter self weight, faster installation speed and better seismic performance Construction quality is easier to be guaranteed, steel can be recycled, more green and environmental protection.

Project introduction the project is located at the intersection of Shenzhen road and Qinglong Road, SHANGPAI Town, Feixi County, covering an area of 161 Mu and a total construction area of 191400 m2, including five single projects: medical complex building, infection building, canteen, hyperbaric oxygen chamber, sewage treatment station and boiler room.

The single assembly rate of the medical complex building is 60.80%, of which the assembly rate of steel structure in the North District reaches 74.09%, and the steel consumption reaches more than 16000 tons.

In the early stage of construction, the project construction unit shall organize experts to review the technical scheme and assembly rate of precast buildings, so as to solve the problems of key parts and key links such as interlayer curtain wall assembly in the process of design and construction in advance.

The EPC Contractor shall organize and carry out theoretical training and practical training for industrial workers.

Steel structure assemblers can work with certificates only after passing the theoretical and practical assessment, so as to ensure the hoisting safety and construction quality of the project.

*** It is also a precast building demonstration project in Anhui Province in 2022.

After the completion of the project, it will become a national first-class children’s Hospital, comprehensively improve the overall diagnosis and treatment level of Pediatrics in Anhui Province, and enable 20 million children in Anhui Province to enjoy national high-quality pediatric medical services in the province.

In recent years, the state has vigorously developed precast buildings, and our city has promoted the multi system development of precast buildings.

In 2021, the newly started precast building area in the city exceeded 10 million square meters, accounting for 24.8% of new buildings, and the newly started precast building area increased by 56.8% year-on-year.

Fabricated steel structure system is widely used in public buildings such as new campus of Changfeng No.

1 middle school, Ziyun square and phase IV of Fujie street, as well as residential buildings such as yingyue Bay and fengqiyuan.

Ziyun square to be delivered..